What We Settle on Your Kuna Parcel First
No two Kuna parcels hand you the same list. These come up on almost every one.
City water or a well. The City of Kuna runs its own water and sewer. Under its current water policy, land outside city limits that can legally annex must annex before connecting. Land that can't needs City Council approval, at the council's option. Without city water, you're on a private well, and the Idaho Department of Water Resources has to approve a drilling permit before the rig arrives. The driller must hold a state license.
City sewer or septic. Kuna's sewer policy uses the same annexation rule. Off the city system, Central District Health issues septic permits in Ada County and watches the test holes get dug first. In Canyon County, it's Southwest District Health. State rules put the drainfield at least 100 feet from any domestic well. They also reserve a second spot, big enough for a full replacement drainfield, that stays vacant with no vehicles driving over it.
Power to the house site. Idaho Power is the electric utility here. A house set back from existing lines becomes an extension project. We file through Idaho Power's construction request portal once the house location is set, and its engineers lay out the route.
Driveway and fire access. If the parcel is in the Kuna Rural Fire District, the district runs its own access and water supply permit, with a site plan. Its guidelines call for at least a 12-foot improved surface on a road serving one or two homes and 13 feet 6 inches of overhead clearance. Past 150 feet, the road needs a turnaround within 150 feet of the house. Set a house deep in a parcel and that turnaround becomes part of the design.
Irrigation water and laterals. Irrigation districts deliver the water here, Boise-Kuna and New York among them. Where a ditch or lateral crosses your land, Idaho Code 42-1209 keeps roads, fences, pipelines, buildings and plantings out of its easement unless the easement holder agrees in writing.
Setbacks. Zoning sets them, and Kuna's residential permit application asks for your parcel's zone up front. We confirm the numbers with whichever planning office has the parcel and draw them to scale on the site plan.
Drainage and grade. Where runoff goes now, where it goes once there's a roof and a driveway, and how the finished floor sits against both.
Want us to look at a specific parcel? Call (208) 906-1650.