New Beginnings Status

New Beginnings Custom Home Journal

Follow New Beginnings from site prep and foundation corrections into framing, openings, roof dry-in, and deck ledgers—weekly field notes from an active Nampa custom home.

Foundation progress for the New Beginnings project after stem wall work and weatherproofing.
Approved progress image: foundation stage after stem wall work and weatherproofing.
StatusFraming in progress
LocationNampa, Idaho
ScopeFoundation through framing

Current Build Phase

New Begginings is progressing through the current build sequence. Recent field notes cover framing, with weekly updates kept public-safe and focused on process rather than private project details.

  • Shear inspection passed
  • House wrap and window openings
  • Roof dry-in underway
  • Interior framing for drywall prep
  • Front and rear deck ledgers
  • Framing

Weekly Progress

Week of May 23, 2026

Site Prep Opens the Build

New Beginnings opened with early site protection, temporary fencing, and the coordination needed to clear the way for foundation work. Excavation followed the next week, including slab removal and crawl-access openings so the footing sequence could start clean.

Early site prep and excavation progress for the New Beginnings Nampa custom home.
Week of June 1, 2026

Footings, Correction, Then Stem Walls

The footing inspection flagged one correction. The team fixed it before pouring, finished vertical bar work, and passed the follow-up inspection by photo review. Stem wall forms went up next so inspection and pour prep could stay on sequence instead of drifting.

Footing and reinforcing work for the New Beginnings custom home project.
Week of June 6, 2026

Foundation Weatherproofed for Backfill

Stem walls were stripped, then weatherproofing went on the walls and over the footings. That handoff matters: once moisture protection is in, the foundation is ready for backfill without rework later. This is the stage shown in the progress image.

Stem wall and weatherproofing progress for the New Beginnings project.
Week of June 8, 2026

Backfill Plus Framing Prep

Electrical prep finished ahead of framing while backfill wrapped up. Before the next phase, the crew coordinated a short punch list: sprinkler line and wire locations, plus hose bib removal, so small site conflicts would not stall floor framing.

Week of June 15, 2026

Floor Framing and Inspection Notes

The framing crew started floor-joist work and handled an inspection note with couplers at the anchor bolts. Work continued into the back deck area, tying structure decisions back to the foundation details already in the ground.

Week of June 22, 2026

Exterior Framing Pivots on Weather

Exterior wall framing moved until rain hit the site. Instead of losing the week, the crew shifted to interior wall framing so structure kept advancing while weather delayed the exterior sequence.

Framing progress for the New Beginnings Nampa custom home, week of June 22, 2026.
Week of June 29, 2026

Roof Cutback for Front Build-Out

Field work focused on cutting back roof and soffit areas for the front build-out. That kind of mid-structure adjustment has to stay coordinated with framing so later openings and exterior transitions land clean.

Roof and soffit cutback progress for the New Beginnings project, week of June 29, 2026.
Week of July 6, 2026

Shear Inspection and Openings

The project passed shear inspection. Framers continued house wrap and window install while roof tear-off moved into dry sheeting so the openings sequence and weather protection stayed tied together.

Week of July 13, 2026

Deck Ledgers and Interior Prep

The team framed an overhang over the side garage man door, cut in skylights, and framed interior walls for sheetrock. Master bath tub wall framing went in, and pressure-treated ledgers were installed for the front and rear decks.

Deck ledger and framing progress for the New Beginnings project, week of July 13, 2026.
Week of July 20, 2026

Field Progress

New Begginings advanced through site work this week. no trades on site. Saturday Sky lights got flashed and dried in ready for roofing.

Week of July 27, 2026

Framing

New Begginings advanced through framing this week. Framing pickup and backing. Blocking for holes in floor. Securing tyvek. Meeting with O to walk the job site. Demoing the front masonry to gwt ready for new stone.